The total cost of the project     

 

= 914.9887 corer  (GOB -880.0497 -34.9390 corer and BUB)

 

Project Start

 

July 1, 015

 

Possible to implement                                  

 

June 30th, 2018

The project planning


Construction of 33/11 KV substation

New = 16, up graded = 17, renovation = 11 Total = 44

 

Establishment of distribution transformers

 

1055


Line Construction

 

 

 

 

 

 

The new line of 33 KV

 

221 km

 

The new line of 11 KV

 


341 km 387 km 396 km 1145 km

11 / 0.4 KV new lines

 


341 km 387 km 396 km 1145 km

 0.4 KV new lines

 


341 km 387 km 396 km 1145 km

Total


341 km 387 km 396 km 1145 km